News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal (opens in new window)
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Operations CXO Status Report

Friday 26 October 2018 9.00am EDT

During the last week the Chandra Operations team completed the procedures and on-board software updates to place Chandra into a new gyroscope configuration with the gyroscope that caused the Oct 10 safe mode in reserve. The procedures were carried out Oct 19. Additional real-time procedures were executed on Oct 20 to dump OBC-A and -B memory as a follow-up to the software updates. The dump will be used to update the baseline memory images maintained on the ground. Science observations resumed Oct 22.

A sequence of maneuvers was carried out Oct 25-26 to provide calibration data required to update the spacecraft knowledge of the active gyros.

The schedule of targets for the next week is still in work at this time.





All spacecraft subsystems continued to support nominal operations.