During the last week Chandra completed the observing schedule as planned. Real time procedures were run Monday evening to perform a controlled ramp-up of the HRC-I microchannel plate high voltage. The HRC microchannel plate was slowly ramped up to same values as used by the A side electronics. A live image was accumulated and AR Lac was easily seen with approximately the expected count rate. Detailed analysis is being performed. Additional real-time procedures were executed during each ground contact to reset the DSN Outage Dead Man Load. The schedule of targets for the next week is shown below and includes an observation of A0620-00 coordinated with VLA and NOAO/LCO, and observations of NGC 205 coordinated with VLA. |
------------------------------------------
MRC 0131-449 ACIS-S GJ 358 ACIS-S Oct 5 SDSSJ0050-0212 ACIS-S SNR 0509-67.5. ACIS-S Radiation Belts Oct 6 J101815.1+462623.9 ACIS-S NGC 205 ACIS-S RBS 797 ACIS-S Oct 7 NGC 205 ACIS-S RBS 797 ACIS-S SDSSJ0047+2640 ACIS-S Oct 8 Radiation Belts Westerlund 1 ACIS-I Oct 9 Orion Nebula Cluster ACIS-S/HETG 2MASS 0201+0117AB ACIS-S Oct 10 A0620-00 ACIS-S 4FGL J0744.0-2525 ACIS-I DSSJ014721.7-091646 ACIS-S MCG -5-23-16 ACIS-S/HETG Radiation Belts Oct 11
------------------------------------------
All spacecraft subsystems continued to support nominal operations.
Return to Status Reports