News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal (opens in new window)
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Operations CXO Status Report

Friday 8 August 2014 9.00am EDT

During the last week Chandra completed the observing schedule as planned.

A real-time procedure was executed on Aug 6 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer.

Chandra passed through the ninth and tenth eclipses of the season on Aug 3 and 6 respectively, with nominal power and thermal performance.

The schedule of targets for the next week is shown below and includes an observation of the Crab coordinated with HST.



------------------------------------------
        Radiation Belts                     Aug 11
        ACT-CLJ0022-0036       ACIS-I
        NGC289                 ACIS-I       Aug 12
        AbellS0295             ACIS-I       Aug 13
        3C154                  ACIS-S
        Radiation Belts
        G115.71+17.52          ACIS-I       Aug 14
        Abell2256              ACIS-I
        NGC3359                ACIS-I       Aug 15
        3C169.1                ACIS-S       Aug 16
        Crab                   ACIS-S
        3C142.1                ACIS-S
        Radiation Belts
        GX3+1                  ACIS-S/HETG  Aug 17
        Abell2256              ACIS-I

------------------------------------------

All spacecraft subsystems continued to support nominal operations.